New Buck O’Neil Bridge Repair Plan Keeps Span Open to Northbound Traffic, Buys Time for Long-Term Solution
November 3, 2017 | | 4 min read
By Kevin Collison
In a big breakthrough for downtown commuters, state highway and city officials have come up with an interim repair plan that avoids closing the Buck O’Neil Bridge entirely and buys time to come up with a hoped-for, permanent replacement.
The proposal would address critical repair needs to the bridge between downtown and the Northland at a cost of about $6 million, and budgets $2 million to study a potential replacement. The span opened in 1956 as the Broadway Bridge.
The approximately six-month project could be accomplished while continuing to allow two lanes of northbound traffic throughout the work, state highway officials said. The southbound highway lanes would be closed for the duration.
That’s a big improvement however, over a previous major overhaul proposal that would have closed the bridge, which carries 40,000 vehicles daily on U.S. Route 169, entirely for two years.
The cost for the proposed interim repair plan would be shared 50-50 by the city and state. If approved, work would begin late next spring or early summer.
Brian Kidwell, local administrator for the Missouri Department of Transportation, said the new plan would provide local officials time to explore ways to fund what most people prefer: a $200 million replacement span that would directly connect with Interstate 35, also known as the West Loop.
“I really think a new bridge has a good shot,” Kidwell said. “It will take time to get it together.”
MoDOT previously had been considering a $51 million overhaul of the existing O’Neil Bridge that would have closed it for two years, added no options for pedestrians and bicyclists, and left the current clumsy connection to I-35 intact, an idea that drew strong community objections.
Kidwell described that option as “super disruptive.”
Instead, transportation advocates want a completely new span with a more westerly alignment that would serve downtown and I-35 traffic better as well as provide additional transportation options. A replacement also could be built while traffic continued to use the existing O’Neil Bridge.
The problem: the ambitious long-term replacement plan would cost at least $200 million, and at this point, MoDOT, which has experienced years of budget cuts, has identified only about half the funding.
“We don’t have it, and Kansas City, Missouri, and the region are working on different scenarios and options for half the cost of a new bridge,” Kidwell said. “There is a tremendous desire and sincere effort to give the public something better.”
The interim repair plan would fix the “worst of the worst” structural problems and also address riverbed erosion issues, Kidwell said. The additional $2 million would begin the environmental study required if a replacement span would be built.
The decision to keep two north-bound lanes open in the interim repair proposal was partly in response to requests by city fire and police officials to keep access open to the Charles Wheeler Downtown Airport, which is served by a fire station based in the River Market.
Kidwell also said to have one-lane open each direction would cause major congestion issues during rush hour. Instead, southbound traffic will be encouraged to use Interstate 29/35 which carries traffic on the Kit Bond Bridge.
A public information meeting on the new O’Neil repair plan is scheduled for Nov. 30 from 2- to 4 p.m. at the Mid-Ameria Regional Council board room.
Complicating matters for downtown commuters, the Kansas Department of Transportation is planning to close the westbound Lewis and Clark Viaduct, which carries I-70 traffic to downtown Kansas City, Kan., for an estimated 18 months beginning early next year. The aging viaduct is being replaced.

Two lanes would remain open to northbound traffic in a new interim repair plan recommended for the Buck O’Neil Bridge. (Rendering courtesy Downtown Council).
Two lanes would remain open to northbound traffic in a new interim repair plan recommended for the Buck O’Neil Bridge. (Rendering courtesy Downtown Council).

One option for a potential replacement bridge would connect it directly to I-35. (Rendering courtesy Downtown Council).
This story appeared originally on the KCUR public radio website.
Reading these stories is free, but telling them is not. Start your monthly gift now to support Flatland’s community-focused reporting.
Related Stories
Nick’s Picks | Roads, Bathrooms, Costco and More …
New Toll Road Opens Kansas City’s first toll road opens this week. Starting Saturday, you’ll pay up to $3.50 to travel the new express lanes on U.S. Highway 69 from 103rd to 151st streets in Overland Park. There are no toll booths — cameras scan your license plate, and a bill arrives by mail. KTAG…
Up From the Ashes: Warwick Theatre Revival Draws Applause
Two years ago, John Cleary met a fellow Kansas City actor for drinks. Their conversation centered on the fate of the Metropolitan Ensemble Theatre. A large portion of the ensemble’s home, the Warwick Theatre, was ash, charred timbers and soot-saturated costumes and props — remnants from a recent massive fire. The destruction was so great…
Nick’s Picks | Baseball, Drones, Romance and More …
Royals Reveal Next week, the Kansas City Royals head to Arizona for Spring Training. And that’s the mayor’s self-imposed deadline to lock in a stadium deal. So, is this finally the week owner John Sherman steps to the plate and unveils where the Royals will build their next home? At last week’s council meeting, Mayor…